Norman Kirk Memorial Pool

This project, commissioned December 2010 is a Community Pool complex consisting of an outdoor 25
metre pool, a 25 metre indoor heated pool, spa pool, leisure pool and toddlers pool.


The pool water services for this project included:

  • Pumping and pressure media filtration for all above systems
  • Piping for all of the above (PVC and ABS)
  • Chemical control systems using Sodium Hypochlorite and CO²
  • Heat exchangers
  • Overflow channel grating.
  • Pumps, piping, valves etc. for water features

 


Duration of pool water services was 18 months (completed December 2010).

 